Location: Sacramento, CA

Client: HP Hood, LLC

Trades: Electrical

Contract Value: $1.5  million


 

Mark III performed the design-assist for a dairy supply facility in Sacramento, CA. This project included the installation of an owner-provided 69 kV redundant substation, and a 12.47 kV distribution infrastructure valued at $4 million. Both substation lineups included transformers, voltage regulators, metering, bussing, breakers, air switches, switch gear, and controls. Additionally, Mark III provided concrete slabs, pits, fencing, and platforms and fabricated the underground utility distribution.